Project Overview
The East Greenwich Solar Carport installation was performed in the summer of 2018. The 1.7 Megawatt carport project took 3 months to install foundations, posts, truss, and purlins. The layout design dictated tight parameters around entrance roof overlaps and utility/sidewalk obstacles.
Project Results
The project was finished on time and met all of the requirements of the layout design. The 164 foundations were completed with no issues on alignment, spacing or elevation. The installation was awarded the “National Excellence Award” from the American Galvanizer’s association.
System Size
1.72 MW
Completion Date
July 2018
Solar Panel
Canadian Solar 330 Watt
Project Scope
Racking Supply & Installation